Tuesday 4 June 2013

Lock up 23/5/13


Hebel finished. Ground floor still to be finished with render and lining board upstairs will be painted later.


Insulation installed.  We also decided to add soundscreen insulation between floors.  Hopefully it will be worth the expense! Electrical fit out completed and AV cables installed. 


No comments:

Post a Comment