CG arranged 3 quotes for us and we independently arranged another 2. We ended up choosing one of the CG arranged quotes as they were able to also remove a very large tree. The communication from this company was very average and we were frustrated that we were not able to determine when our demolition was going to occur. We had all our services abolished within a 2 week time frame but were left waiting for a demolition date. We had to reschedule our pool dig twice because of this. After many months of planning we were keen to get to site! In the end we lost a couple of weeks which adds to extra rental costs. The actual demolition work was excellent however and took approximately 1 week. We did sell the kitchen oven and dishwasher otherwise left the house intact. We had extra asbestos located during the demolition which meant increased costs. Interestingly nothing (timber etc) seemed to get stripped or separated out on site.